Short answer
- Definition: day and month of each year corresponding to the date of expiry of the certificate (ISM 1.1.11; SOLAS I/2(n))
- Trap: counted from the expiry date, not the issue date
- Survey window: six months, three months before to three months after the anniversary date (A.1207(34) general 1.3)
- DOC: annual verification within three months before or after the anniversary date (ISM 13.4)
- SMC: at least one intermediate verification; if only one on a five-year certificate, between the second and third anniversary date (ISM 13.8)
- India: rule 8(2)(b) counts the DOC window from each anniversary of issuance; rule 9(5) SMC five years
- Chief Engineer: plans surveys and audits inside the windows from each certificate’s expiry date
| Activity | Window counted from the anniversary date |
|---|---|
| Annual survey | Three months before or after each anniversary date |
| Intermediate survey | Three months before or after the second or the third anniversary date, in place of one annual |
| Periodical survey, safety equipment | Three months before or after the second or third anniversary date |
| Periodical survey, safety radio | Three months before or after each anniversary date |
| Maritime labour certificate intermediate inspection | Between the second and third anniversary dates |
Explained in detail: MLC 2006 Standard A5.1.3 (maritime labour certificate)
Rules mentioned: SOLAS
Full answer
The full answer explains each point step by step, with the regulations and figures behind it and the discussion from other candidates. It is in the MEO Class I section of the Marine One forum, open to members enrolled for the MEO Class I exam.