Short answer
- NC: an observed situation where objective evidence indicates the non-fulfilment of a specified requirement (ISM Code 1.1.9)
- Not an NC: an observation, a statement of fact made during a safety management audit and substantiated by objective evidence (1.1.8)
- Major NC: a deviation posing a serious threat to safety or a serious risk to the environment that requires immediate corrective action, or lack of effective and systematic implementation of a requirement of the Code (1.1.10)
- India: a major NC found at an audit needs immediate corrective action, verified by the auditor; no certificate issued or renewed until it is completed (rule 13(6))
- Closing: the company should establish procedures for corrective action, including measures intended to prevent recurrence (ISM Code 9.2)
- Time: for corrective actions, guidance says not normally more than three months (A.1188(33))
- Trap: an NC from a previous audit left uncorrected in the stipulated time is deemed a major non-conformity in India (rule 14(3))
- Who acts: the management personnel responsible for the area should take timely corrective action (12.7)
flowchart LR
A["Finding raised: audits, inspections or day-to-day work"] --> B["Reported under the company procedure"]
B --> C["Investigated; cause found"]
C --> D["Situation put right"]
D --> E["The evaluation may lead to amendments to procedures and instructions, or new ones"]
E --> F["Responsible person should monitor the follow-up and closing-out"]
F --> G["Closed out; India: findings and corrective actions documented and retained"]
Explained in detail: ISM Code §9 (non-conformities and accidents)
Rules mentioned: ISM Code
Full answer
The full answer explains each point step by step, with the regulations and figures behind it and the discussion from other candidates. It is in the MEO Class I section of the Marine One forum, open to members enrolled for the MEO Class I exam.