What do you do as Chief Engineer while loading an IMSBC cargo?
Short answer
flowchart LR A["Cargo information and declaration confirmed"] --> B["Group A: moisture below the TML"] A --> C["Group B: ventilation, atmosphere, self-heating"] B --> D["Loading plan agreed under the BLU Code"] C --> D D --> E["Deballast in sequence; shear force and bending moment within limits"] E --> F["Stop if a limit approaches or a ballast pump fails"] F --> G["Holds trimmed, final condition confirmed"]
- Groups: A may liquefy above its transportable moisture limit (TML); B has a chemical hazard (gas, self-heating, oxygen depletion, corrosion); C neither.
- Before loading (§4.2.2, §4.2.3): the shipper’s information and signed declaration: BCSN, group, IMO class, UN number, and for Group A the TML and actual moisture with a certificate.
- Group A: moisture below the TML on a certificate sampled close to loading; any doubt (rain, splatter, a can test) means no loading.
- Group B: schedule ventilation, spaces treated as oxygen-depleted or toxic (gas testing before entry), no hot work where gas is possible, self-heating monitored.
- My own job: deballast in the sequence agreed under the BLU Code plan, rate within the ballast pumps, shear force and bending moment within the loading instrument limits (IACS UR S1, S1A); stop if a limit approaches.
- Completion: holds trimmed, final stress and stability within limits, records complete; within the ISPS security regime (§11).
Full answer
The full answer explains each point step by step, with the regulations and figures behind it and the discussion from other candidates. It is in the MEO Class I section of the Marine One forum, open to members enrolled for the MEO Class I exam.