What is the BLU Code, and how does it keep a bulk carrier safe during loading and unloading?
Short answer
flowchart LR A["Information exchange before arrival (section 3)"] --> B["Suitability of ship and terminal confirmed (section 2)"] B --> C["Agreed loading or unloading plan and ship-shore safety checklist (section 4)"] C --> D["Operation to the plan: ballast in step, stresses monitored (sections 5 and 6)"] D --> E["Deviation: stop, agree, record"]
- What: the Code of Practice for the Safe Loading and Unloading of Bulk Carriers (A.862(20), 1997), recommendatory but given force by SOLAS VI/7: master and terminal representative agree a plan within the ship’s limits.
- Why: terminals load thousands of tonnes an hour; wrong sequence, too fast, uneven, or deballasting that cannot keep pace over-stresses the hull girder (shear forces and bending moments).
- Six sections: 1 definitions; 2 suitability of ship and terminal; 3 information exchange before arrival; 4 the agreed plan and the ship-shore safety checklist; 5 loading with ballast handling; 6 unloading with ballast handling; the annexes give the forms.
- Key messages: an agreed, documented plan; shear force and bending moment limits never exceeded (loading instrument); communication, and either side can stop the operation.
- As Chief Engineer: the ballast plant (pumps, lines, eductors) must match the agreed rate, or the plan fails and the hull is over-stressed; I support the loading-instrument monitoring.
Full answer
The full answer explains each point step by step, with the regulations and figures behind it and the discussion from other candidates. It is in the MEO Class I section of the Marine One forum, open to members enrolled for the MEO Class I exam.