Who approves a Planned Maintenance System and on what basis is the maintenance carried out?
Short answer
flowchart LR
A[Classification Society] -->|approves| B[PMS per UR Z20]
B --> C[Maintenance basis]
C --> D[Manufacturer recommendations]
C --> E[Running hours]
C --> F[Calendar intervals]
C --> G[Condition monitoring]
C --> H[Operator experience]
- Approval authority: Classification society (IACS Member) under IACS UR Z20
- Basis of maintenance: manufacturer’s recommendations, running hours, calendar intervals, condition monitoring, documented operator experience
- SMS framework: ISM Code section 10 requires planned, procedure-driven, recorded maintenance
- Indian application: MS Act 2025 s.147 applies ISM Code to Indian ships
- Chief Engineer role: responsible on board for PMS, signs overhaul documentation, ensures maintenance per approved scheme
Full answer
The full answer explains each point step by step, with the regulations and figures behind it and the discussion from other candidates. It is in the MEO Class I section of the Marine One forum, open to members enrolled for the MEO Class I exam.