ISM Code §12

What it requires, why examiners ask it, the key figures and how it works on board.

Updated . Written from the regulation texts; paraphrased, with figures as the instruments give them.

What it requires

Section 12 of the ISM (International Safety Management) Code is the company's own check on its safety management system (SMS). It has seven parts.

  • Internal safety audits (12.1). The company audits each ship and its shore office. The aim is to verify that safety and pollution-prevention work follows the SMS. The interval must not exceed twelve months. In exceptional circumstances it may run over by up to three months, but no more.
  • Checking delegated tasks (12.2). Some ISM work may be handed to others, such as a crew manager. The company must check from time to time that they act in line with the company's own ISM duties.
  • Evaluating effectiveness (12.3). The company must periodically judge whether the SMS actually works. It does this under procedures it has set itself. This is the management review.
  • Documented procedures (12.4). Audits, and any corrective action that follows, are carried out under written procedures.
  • Independent auditors (12.5). Auditors should not audit their own area of work. The exception is a company so small, or of such a nature, that this is impracticable.
  • Telling the people responsible (12.6). Audit and review results go to everyone who has responsibility in the area concerned.
  • Corrective action (12.7). The managers responsible for that area must correct the deficiencies found, and do so in good time.

The ISM Code is worded with "should". It is still mandatory. SOLAS chapter IX, regulation 3 requires the company and the ship to comply with the Code and treats its requirements as mandatory.

Why it is asked

Section 12 is the "check and act" part of the SMS. Examiners use it to see whether a candidate knows how a company finds and fixes its own weak points.

Typical questions are:

  • How do you prepare the ship and its documents for an ISM audit?
  • What is the difference between a company (internal) audit and an external audit by the flag or its recognised organisation?
  • What are internal audits and the management review? Write short notes on each.
  • How are follow-up and verification activities controlled, and why does record keeping matter?
  • How does the SMS achieve continuous improvement?

The examiner looks for the twelve-month interval and the three-month limit on extension. They also look for auditor independence, and for the link from audit findings to corrective action and records. A Chief Engineer candidate should explain how engine-room findings are closed out.

Regulations and key figures

Instrument Locus What it requires
ISM Code Section 12.1 Company carries out internal safety audits on board and ashore at intervals not exceeding twelve months; in exceptional circumstances, may be exceeded by not more than three months
ISM Code Section 12.2 Company periodically verifies that those doing delegated ISM-related tasks act in line with the company's responsibilities
ISM Code Section 12.3 Company periodically evaluates the effectiveness of the SMS under its own procedures
ISM Code Section 12.4 Audits and possible corrective actions follow documented procedures
ISM Code Section 12.5 Auditors independent of the area audited, unless impracticable because of the company's size and nature
ISM Code Section 12.6 Audit and review results brought to the attention of all personnel responsible in the area
ISM Code Section 12.7 Responsible management personnel take timely corrective action on deficiencies
ISM Code Section 5.1.5 Master's documented duty includes periodically reviewing the SMS and reporting its deficiencies to shore management
ISM Code Section 9.1 and 9.2 Non-conformities, accidents and hazardous situations reported, investigated and analysed; corrective action includes measures to prevent recurrence
ISM Code Section 1.1.9 and 1.1.10 Definitions of non-conformity and major non-conformity (a deviation posing a serious threat, needing immediate corrective action)
ISM Code Section 13.4 Document of Compliance verified annually within three months before or after the anniversary date
ISM Code Section 13.8 Safety Management Certificate has at least one intermediate verification; if only one and the certificate runs five years, it falls between the second and third anniversary dates
ISM Code Section 14.4.3 Interim Safety Management Certificate issued only if the company has planned the ship's internal audit within three months
SOLAS Chapter IX, regulation 3.1 Company and ship comply with the ISM Code; its requirements are treated as mandatory
SOLAS Chapter IX, regulation 6.1 Administration, or its recognised organisation, periodically verifies that the ship's SMS functions properly
Merchant Shipping Act 2025 Section 147 Every vessel, company or port is surveyed, audited and certified for compliance with the applicable conventions, including the Safety Convention

On board

The company runs the internal audit. People on board prepare for it, take part in it, and close its findings.

Chief Engineer (Class 1)

  • Keeps the engine department's SMS records complete and current: maintenance records, checklists, drill records and non-conformity reports.
  • Reviews earlier audit findings for the engine room and confirms that each corrective action is closed with evidence.
  • Gives the auditor access to engine-room spaces, records and people.
  • Agrees corrective actions and target dates for engine-room findings, and sees that they are done on time.
  • Supports the Master's own review of the SMS, which the Master reports to shore management (section 5.1.5).

Second Engineer (Class 2)

  • Keeps the planned maintenance records and engine-room logs in order. These are the main evidence an auditor checks.
  • Carries out the engine-room corrective actions assigned by the Chief Engineer and records their completion.
  • Briefs junior engineers and ratings on findings that affect their work.

Engineer Officer of the Watch (Class 4)

  • Keeps watch records, checklists and logbooks accurate. Auditors often check these against what they see.
  • Reports non-conformities, accidents and hazardous situations through the SMS reporting procedure (section 9.1).
  • Answers auditor questions on their own duties and on emergency procedures.

Electro-Technical Officer (ETO)

  • Keeps records for electrical, electronic and control equipment in order, including tests of stand-by and safety systems.
  • Closes findings on that equipment and records the evidence.

India. The Merchant Shipping Act 2025 requires every vessel, company or port to be surveyed, audited and certified for compliance with the applicable conventions, including SOLAS (section 147). For the Act's safety part, the "company" has the same meaning as in the ISM Code (section 115).

Related topics

  • ISM Code, section 1: objectives and functional requirements of the SMS
  • ISM Code, section 5: the Master's responsibility and authority
  • ISM Code, section 9: reports and analysis of non-conformities and accidents
  • ISM Code, section 10: maintenance of the ship and equipment
  • ISM Code, section 11: documentation
  • ISM Code, section 13: certification and periodical verification
  • ISM Code, section 14: interim certification

Traps and follow-ups

  • Wrong interval. The limit is "not exceeding twelve months". An extension is allowed only in exceptional circumstances, and only by up to three months. It is not a routine fifteen-month cycle.
  • Mixing up internal and external audits. Section 12 audits are run by the company. The flag or its recognised organisation carries out the external verifications under section 13 and SOLAS IX/6.
  • Audit versus review. An audit checks that the SMS is being followed (12.1). The review judges whether the SMS is effective (12.3). Candidates often treat them as one thing.
  • Auditor independence. A ship's own officer should not audit their own department. Independence can be relaxed only where it is impracticable due to the company's size and nature.
  • "Should" means optional. It does not. SOLAS IX/3 makes the Code mandatory.
  • Ending at the finding. The section ends with timely corrective action by the responsible managers (12.7), not with the audit report.

Likely follow-ups:

  • What is a non-conformity, and what makes one a major non-conformity?
  • When must the Document of Compliance and Safety Management Certificate be verified?
  • What internal-audit condition applies before an Interim Safety Management Certificate is issued?
  • How would you, as Chief Engineer, show objective evidence that a finding has been closed?

Short forms on this page: CLC: Civil Liability Convention.